Meeting 4/25/13

Status Report for Week #8-2

04/25/13

Tasks accomplished

  1. Tested 3 more users as a team during Thursday's meeting.

Tasks In Progress

  1. User Testing.

Tasks Planned

  1. Finish user testing tomorrow (Friday) with the final user.
  2. Gather everything required for submission on Monday.

Issues

  1. Known Issue: iOS support is still not fully there.

Metrics

(Times below are since the last update unless otherwise noted.)
  1. Effort expended on project for each person and the total for the team for that week and a running total.
  2. Christoffer Rosen: 1.5 Hours
  3. Emma Nelson: 1.5 Hours
  4. Sam Lucidi: 1.5 Hours
  5. Mustafa All-Sahihi: 1.5 Hours
  6. Ben Hare: 1.5 Hours
  7. Total: 162.45 Hours

Tuesday, April 23, 2013

Meeting 4/23/13

Status Report for Week #8-1

04/23/13

Tasks accomplished

  1. Sam fixed a bug where the trash can icon would not show up.
  2. Emma printed all the consent forms and checked out an Android tablet to use for testing from the Honors Lab.
  3. Ben and Mustafa updated the surveys for usability testing.
  4. Chris made the QR code and encoded the NFC Chip.
  5. Completed testing with 4 Users as a team during today's meeting time.

Tasks In Progress

  1. Sam and Chris will be correcting bugs as they are found and as they have time.

Tasks Planned

  1. Test 3 more users during Thursday's meeting.
  2. Test 1 more user, Michael Roppolo, on Friday at 3 PM.
The whole team is meeting for both of these times.

Issues

  1. No team problems.
  2. Known bug: on phones larger text descriptions are overlapped by buttons for order items.
  3. Known bug: the cart screen does not appear on any iOS device.
  4. Known bug: if you tap back before the screen finishes loading, it takes you back 2 screens. This has been determined as a bug in Sencha.

Metrics

(Times below are since the last update unless otherwise noted.)
  1. Effort expended on project for each person and the total for the team for that week and a running total.
  2. Christoffer Rosen: 1.5 Hours
  3. Emma Nelson: 1.75 Hours
  4. Sam Lucidi: 1.5 Hours
  5. Mustafa All-Sahihi: 1.5 Hours
  6. Ben Hare: 1.5 Hours
  7. Total: 154.95 Hours

Thursday, April 18, 2013

Meeting 4/18/13

Status Report for Week #7-2

04/18/13

Tasks accomplished

  1. Functional Prototype
    1. Sam and Chris were awesome and got it all working. :)
    2. Ben and Mustafa took care of the "little stuff" - correcting spelling, README, etc.
  2. Test Plan and related materials are ready to go!
    1. Emma prepared the surveys
    2. Chris has the NFC chip and QR Code

Tasks In Progress

  1. User Testing
    1. First time with users is Monday 12-2 pm
    2. Mustafa is responsible for bringing the magnet for hanging the QR code.
    3. The test plan specifies who is in-charge of making sure things get done.

Tasks Planned For Next Week

  1. Complete user testing

Issues

  1. None

Metrics

(Times below are since the last update unless otherwise noted.)
  1. Effort expended on project for each person and the total for the team for that week and a running total.
  2. Christoffer Rosen: 7.5 Hours
  3. Emma Nelson: 0.75 Hours
  4. Sam Lucidi: 4.5 Hours
  5. Mustafa All-Sahihi: 1.75 Hours
  6. Ben Hare: 1.75 Hours
  7. Total: 147.2 Hours

Wednesday, April 17, 2013

Meeting 4/16/13

Status Report for Week #7-1

4/16/13

Tasks accomplished

  1. Review feedback on the test plan. - Emma and Chris
  2. Submitted Heuristic Evaluation paperwork - Emma

Tasks In Progress

  1. 100% functional prototype - Mostly Chris and Sam with help from everyone else
    • Just want it working, make it pretty later

Tasks Planned For Next Meeting

  1. Make the prototype prettier!

Issues

  1. None

Metrics

(Times below are since the last update unless otherwise noted.)
  1. Effort expended on project for each person and the total for the team for that week and a running total.
  2. Christoffer Rosen: 1.5 Hours
  3. Emma Nelson: 4.5 Hours
  4. Sam Lucidi: 9.5 Hours
  5. Mustafa All-Sahihi: 1.25 Hours
  6. Ben Hare: 1.5 Hours
  7. Total: 129.35 Hours

Friday, April 12, 2013

Week 6

Status Report for Week #6

04/11/13

Tasks accomplished

  1. Emma made the main menu buttons take up the whole height of the screen.
  2. Chris created and got the Favorites buttons working.
  3. Chris, Ben and Sam have been chipping away at the tasks listed in the previous post. About 50% are now completed.

Tasks In Progress

  1. The test plan is in progress. Emma started it. She and Chris continued to work on it during Wednesday's meeting. Emma will take care of the last few bits over the weekend.
  2. The testing materials are also in the works.
    1. Emma will make the background and post-evaluation surveys.
    2. Chris will create the QR-Code and encode the NFC Chip.
  3. The application still needs "shopping cart" functionality and related screens.

Tasks Planned For Next Week

  1. Test plan needs to be completed for Monday's meeting.
  2. Finish the last of the functionality and screens for testing during week 8.

Issues

  1. Mustafa and Ben bailed on Wednesday's meeting without letting anyone know in advance.
  2. During Wednesday's meeting it was realized by those present that Mustafa has yet to visibly contribute to the project beyond meeting attendance.

Metrics

(Times below are since the last update unless otherwise noted.)
  1. Effort expended on project for each person and the total for the team for that week and a running total.
  2. Christoffer Rosen: 5.25 Hours
  3. Emma Nelson: 3.25 Hours
  4. Sam Lucidi: 0.75 Hours (Reported)
  5. Mustafa All-Sahihi: 0.75 Hours (Reported)
  6. Ben Hare: 0.75 Hours (Reported)
  7. Total: 110.85 Hours

Thursday, April 4, 2013

Meeting 4/4/13

Status Report for Week #5-2

4/4/13

Tasks accomplished

  1. Established what else we need to complete as a team to have a fully working proof of concept product.

Tasks In Progress

Working on the remaining bits of functionality to get the project to be a functional prototype.
  • ADJUST:: Resize the main menu buttons to take up full screen space.
  • ADJUST:: Place Menu :- Group/divide by station, finish details page. Add to cart. Add cart view somewhere. Add place order button on the button. -- Assigned to Sam (In Progress)
  • ADD :: Favorites :- Click on it should get you get details. Need to user a store/local storage not hard code list items.
  • ADJUST :: Order History: Center the Favorite and Cart buttons. -- Ben Hare (in progress)
  • ADJUST :: Order History: Enlarge the Favorite and Cart buttons. -- Ben Hare (in progress)
  • ADD :: Order History: Make the heart selection update the heart image.
  • ADD :: Order History: Add functionality to heart and cart buttons.
  • ADD :: Favorites: Add functionality to cart button.
  • ADD :: Cart store: need a list to hold orders’ items.
  • ADD :: Default Return Confirmation Page. Number that increments each time that makes it pretend that it works.

Tasks Planned For Next Week

  1. Complete as much of the defined tasks as possible.
  2. Start on the test plan.

Issues

  1. None

Metrics

(Times below are since the last update unless otherwise noted.)
  1. Effort expended on project for each person and the total for the team for that week and a running total.
  2. Christoffer Rosen: 1 Hour
  3. Emma Nelson: 1.5 Hours
  4. Sam Lucidi: 1.5 Hours
  5. Mustafa All-Sahihi: 0 Hourhs - missed the meeting
  6. Ben Hare: 1.5 Hours
  7. Total: 99.6 Hours

Meeting 4/2/13

Status Report for Week #5-1

04/02/13

Tasks accomplished

  1. Design document is complete and submitted!
    • The whole team pulled together to get it finished.
    • Emma submitted the first copy.
    • Sam submitted an improved version a few hours later.
  2. The app now has improved styles!
    • Courtesy of the hard work put in by Emma, Sam and Chris.

Tasks In Progress

  1. App development is underway!
    • Whole team is busy chugging away.

Tasks Planned For Next Meeting

  1. Start on the test plan.
    • Began in class on Wednesday
    • The whole team will contribute.
  2. Continue working on the app.
    • The whole team will contribute.

Issues

  1. None

Metrics

(Times below are since the last update unless otherwise noted.)
  1. Effort expended on project for each person and the total for the team for that week and a running total.
  2. Christoffer Rosen: 4 Hours
  3. Emma Nelson: 2 Hours
  4. Sam Lucidi: 3.5 Hours
  5. Mustafa All-Sahihi: 1.5 Hours
  6. Ben Hare:1.5 Hours
  7. Total: 94.1 Hours

Meeting 4/1/13

Status Report for Week #5-0

4/1/13

Tasks accomplished

  1. Figured out how to change the style sheet for the UI. - Emma and Chris
  2. Completed a ER Diagram - Emma and Ben

Tasks In Progress

  1. Basic UI prototype is in development - whole team.
  2. Design Document and diagrams are in progress - whole team.

Tasks Planned For Next Meeting

  1. Finish the Design Document and add screen shots from the prototype.

Issues

  1. None

Metrics

(Times below are since the last update unless otherwise noted.)
  1. Effort expended on project for each person and the total for the team for that week and a running total.
  2. Christoffer Rosen: 5 Hours
  3. Emma Nelson: 3.5 Hours
  4. Sam Lucidi: 2.5 Hours
  5. Mustafa All-Sahihi: 2.5 Hours
  6. Ben Hare: 2.5 Hours
  7. Total: 81.6 Hours