Meeting 4/1/13
Status Report for Week #5-0
4/1/13
Tasks accomplished
- Figured out how to change the style sheet for the UI. - Emma and Chris
- Completed a ER Diagram - Emma and Ben
Tasks In Progress
- Basic UI prototype is in development - whole team.
- Design Document and diagrams are in progress - whole team.
Tasks Planned For Next Meeting
- Finish the Design Document and add screen shots from the prototype.
Issues
- None
Metrics
(Times below are since the last update unless otherwise noted.)
- Effort expended on project for each person and the total for the team for that week and a running total.
- Christoffer Rosen: 5 Hours
- Emma Nelson: 3.5 Hours
- Sam Lucidi: 2.5 Hours
- Mustafa All-Sahihi: 2.5 Hours
- Ben Hare: 2.5 Hours
- Total: 81.6 Hours