Status Report for Week #9
05/02/13
Tasks accomplished
- Completed slide deck for presentation on Monday as a team
- Chris updated the app to use a unified menu instead of the old menu screen
- Chris fixed the cart feature, so now the cart works on both Android and iOS
Tasks In Progress
- Emma is working on the styling to give the app RIT styles so it isn't platform specific
- Ben is removing the shields (confirmation popups)
- Sam is continuing to fix bugs
Tasks Planned For Next Week
- Code Freeze is Friday at 11:59 PM
- Final Presentation is Monday at 8 AM
Issues
- None
Metrics
(Times below are since the last update unless otherwise noted.)
- Effort expended on project for each person and the total for the team for that week and a running total.
- Christoffer Rosen: 7.5 Hours
- Emma Nelson: 1.5 Hours
- Sam Lucidi: 1.5 Hours
- Mustafa All-Sahihi: 1.5 Hours
- Ben Hare: 1.5 Hours
- Total: 175.95 Hours